Updated old fascia

PROJECT in Aylsham

New fascia boards
Old fascia

Removed the existing fascia boarding and reconfigured supports as the previous installation had been inadequately fixed with roof nails, causing twisting and misalignment.

  • Erected a 5m access tower to reach all working areas.
  • Installed new uPVC coverboard sections onto the reconfigured boarding.
  • Secured the reconfigured boarding to soffits and walls using adhesives.
  • Added trims to the brick sides and undersides to provide a neat finish

Access was time-consuming, requiring the tower to be erected and dismantled multiple times.